Asta Natural Order Hierarchy & WBS

I have a schedule file for Asta that needs to be imported into P6.

The problem that I am having is that the schedule was created using the "Natural Order Hierarchy" instead of WBS.

Is there a function that copies the "Natural Order Hierarchy" into a WBS and keeps both of them assoicated with eachother?

M
Mike Testro 👤 Member for 20 years 5 months

Hi Peter and Matt
Asta Powerproject develops its own WBS system or you can create your own.
Any WBS is transcribed to P6 along with the rest of the data.
You can then make use of it as usual.
Best regards
Mike Testro

M
Matt Mills 👤 Member for 12 years 3 months

Peter,

I am also having this issue. Did you have any luck on this?

Thanks,

Matt

 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts