Weekly S curve for progress

P
Paul Jones 👤 Member for 8 years 11 months

Hi- any know how to set weekly s curves for progress reporting?

Thanks

B
Ben Taunt 👤 Member for 14 years 4 months

And don't forget the new "EVA Reporter" export tool, which has superseded the older Progress Expert macro and is now included in all versions from 14 onwards...

M
Mike Testro 👤 Member for 20 years 5 months

Hi Paul

Can be cost but the better measure is resource hours or even labour costs. days progress.

Another is planned days progress over actual 

Expenditure of cost is not a true reflection of progress.

I call this the Golden Tap Syndrome - A gold tap costs 100 time a chrome one and takes the same time to fit.

Best regards

Mike T.

P
Paul Jones 👤 Member for 8 years 11 months

Thanks mike, is this done through the resource graphs set as cost centres?

M
Mike Testro 👤 Member for 20 years 5 months

Hi Paul

You can set up any histgrams comparing planned with actual with a multiple set of data.

The graphs though are better presented on a spreadsheet when the data is exported.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts