Copying Custom Calendar between projects

J
Jeff Raykos 👤 Member for 8 years 4 months

I created a custom calendar for one project and want to use the same calendar for another project.  How do I copy it from one project to another?

Jeff

J
Jeff Raykos 👤 Member for 8 years 4 months

Thanks Mike.  I did try the copy and paste but maybe I wasn't doing it correctly.  I was able to copy a task, and paste it into the new schedule and it carried the calendar with it.

Thanks again!

Jeff

M
Mike Testro 👤 Member for 20 years 5 months

Hi Jeff

Highlight and copy the calendar you want.

Go to the new project and copy the calendar.

If the calendar wizard pops up then disable it first.

Alternatively copy a single task and copy it into the new projoject and it should bring all the other objects with it for you to retain or de select.

Best regards

Mike T.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts