Hello,
I was hoping someone can help. I have had to add a substantial number activities to my programme due to client variations and I have now linked all of the activities. The trouble is my programme now looks like a spiders web due to the large number of diagonal links. Is there a way to format the appearance of links so they are drawn in a horizontal and vertical fashion? Any help or advice would be gladly received.
Thanks in advance
David
Hello Mike.
I am having some issue with linking activities, do you know of any linking software to speed up my linking logics or any advice to get my linking accurate.
Please advise
Mike,
Thanks for your response my programme looks much neater.
David
Hi David - welcome to planning planet.
Use the Curved Link function so that every vertical link is shown curved.
Also you can hide all non driving diagonal links.
Makes everything much clearer.
Best regards
Mike Testro