I downloaded free trial of latest ASTA version. ried to type a new programme, However, when I tried to create a milestone with '0' on duration column it wont allow me to do that. Normally on a milestone start date and finish time is same. But in my programme there is one day difference between start and finish time. It wont allow me to change it into same date on both columns. How do I create milestone? It seems some sort of setting but I cant figure it out ant help will be greately appreciated
Milestone
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Anu - Welcome to planning planet.
There are a number of ways to create a milesstone.
1. Type "0d" days in the duration field.
2. Right click the task and select Options > Change Into > Milestone
3. Hold the end of the task and drag sharp left to turn it into a milestone.
I hope that helps.
Best regards
Mike Testro