Hello Fellow Planners,
I created a contract baseline at the initiation of my project and i have progressed the project since then so activity bars have obviously shifted fowards and backwards. I want to display my baseline finish dates on the chart next to each activity to make it easier for my client to see where each tasks SHOULD have been finishing. But for some reason Asta is not allowing me to.
I usually right click on the bar>Format Bar Chart>Task, then go to the task data display. On the 'left data display' drop down, it allows me to select the same selections as the 'Add Column' function to display info on the chart. When i select finish, it only shows the finish dates of the task which are completed (100 Percent Complete), tasks that are still in progress are left blank. I want it to display the baseline dates so the finish date can be displayed whether the task has been completed or not.
Does anyone know how to do this? Or is there a reasonable alternative?
Thanks in advance!!!
Thank you so much Charlotte exactly what i was looking for.
Cheers for both of your help!
Hi Charlotte
Thanks for that input - learned something new today.
Best regards
Mike T.
Hi Ben,
There is a way that you can show this, you need to use text annotations. Firstly draw and attach a text annotation onto the end of a bar/task, then right click inside of the annotation and you can select a field, go to the date category and choose finish, a box of options will appear allowing you to chose between live data and baselines. Now you should have the finish date of one task, you now need to right click on the annotation again, choose properties from the drop down list, the properties box will then appear, there should be a box that says 'Make Auto Annotation', select this and every task will pick up the end date of your baseline.
Regards,
Charlotte
Hi Ben
The baseline display is only a shadow of the saved baseline programme.
I have not tried this before but try opening the baseline programme and adding the dates to that - it may come up on the main chart.
Be careful because some changes to the baseline chart will prevent future merges.
Best regards
Mike Testro
Hey mike
Cheers for your help. But i think that is only to display baseline dates in the Column section and not on the Bar chart itself. I have tried to add the dates onto the chart via the 'Format Bar chart' function, but it will only allow me to add the original 'Finish' and will not allow me to change it to the baseline finish. Maybe i should just stick the baseline bar and start/finish variance there instead.
Ben
Hi Ben
You can show the planned start and finish of your baseline in the Left Hand data columns.
Create a new column for Start and in the data box select the appropriate baseline.
Do the same for Finish.
You will then have a direct comparison - you can also show the difference in your time unit.
Another way is to display the Baseline in its own line but that doubles the space on the chart.
Best regards
Mike Testro