Hi Guys,
I have created a few filters and coloured my wbs structure using the heirarchy appearance.
However, when I apply a filter, my heirachy appearance structure doesn't follow through with the filter. Rather it becomes a spreadsheet list of what my filter has found without the colour.
Any idea on how i can set this up on filters?
Thank you in advance.
Regards,
Farhad
Hi Scott,
This sounds like a complicated issue to understand - can you give the helpdesk a call so they can investigate properly? 01844 261609.
Thanks,
Ben
Good Afternoon,
Just Facing the similar problem on version 14.0.03 of Asta, when setting up a filter the summary bar dates are not following through with the filtered tasks, it is retaining its dates for the original section, other than what has just been filtered.
In this version, it allows you to click on the code in the code library on the left-hand pane and the summary bars follow the filtered dates. However, this seems to mess with printing layout (revision numbers, descriptions and such disappearing) and It will not let me to re-enter it.
Is there any solution to this yet, preferably a way to use the filter option and get the summary bar to follow the dates?
Thanks, in advance
Scott
Hi Farhad
Asta WBS does not work the same as in P6.
In Asta a WBS is optional not mandatory.
I cannot help further but the Asta support team will tell you what to do if it is possible.
Best regards
Mike Testro