Dear,
Could I just print the line of balance graph instead of print the Gannt Chart together with the line of balance?
Regards,
Gary Lo
Dear,
Could I just print the line of balance graph instead of print the Gannt Chart together with the line of balance?
Regards,
Gary Lo
Dear,
Could I export the line of balance graph to Excel to make modification?
Regards,
Gary Lo
Dear,
Could I have both the line of balance baseline and actual progress be shown at the same time?
Regards,
Gary Lo
Hi Gary Lo,
Yes - on your Line of Balance graph, right-click and chose "Show Standalone". This opens a new tab within Asta Powerproject with the gantt chart toggled off. If you now look at Print Preview, you will see that only the LoB graph is included in your print out.
Thanks,
Ben @ Asta Powerproject