Negative Values For Task Allocations (Cost / Income)

Hi All,

 

Does anyone know if it's possible to have a negative value against a income / cost?

 

Reason for wanting to do this, is that I have an a highway maintenance contract where the client has given us anticipated spends against a list of tasks, but the actual spend was less. Rather than go through and adjust all the anticiapted spends, I was hoping to insert a new task with a negative value against it which represented the sum of the underspend.

 

Kind Regards,

 

Chris

 

B
Ben Taunt 👤 Member for 14 years 4 months

Hi Chris,

Whilst I agree with Craig's suggestion, for reference you can't have a negative cost.  If you try entering one, Asta Powerproject will chuck up a warning stating the value must be greater than zero.  That is the point of the alternative income field within Asta - other software which has no concept of income does allow you to have a negative cost but only to get around that deficency.

So I guess you could use the income field to record the underspend...?  As the net amount would therefore be orginial cost less the underspend...?  Sounds messy though.

Cheers,

Ben @ Asta

C
Craig Adams 👤 Member for 14 years 5 months

Hi Chris,

Wouldn't you just enter actual cost so you could use Asta cost functions?

Kind regards,

Craig

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts