Hi All,
Does anyone out there know of a way to display the level (i.e. in the chart structure) that a line (summay or bar etc.) is at?
I know you can use the Show To Level button, but was after something that could display in the column of that line automatically. I thought that perhaps it could be done through a forrmula, but after hours of trial & error (all error) I cannot see how.
Any info on this would be appreciated, even if its to say it can't be done.
Regards,
Chris
Thanks Mike.
I was after an automated way of doing it - I'll assume as no other answers that it can't be done.
Chris.
Hi Chris
I use a colour code to differentiate the various levels.
The code is then displayed in the Code Column - even though that particular code is not used on the chart display.
Best regards
Mike Testro
BTW - I have cleared your double entry.