Hello Experts,
Plz help for the the follwing
a) How to set up a filter or which filter can be used to view the complete critical path in the whole project?
b) How to convert v12 file into version 10 file with all features and activities ?
Thanks,
Hello Experts,
Plz help for the the follwing
a) How to set up a filter or which filter can be used to view the complete critical path in the whole project?
b) How to convert v12 file into version 10 file with all features and activities ?
Thanks,
Thats great Mike.
Thanks
Hi Chris
Using File > Save As > you can go down to v 11.
From there you may be able to go down further.
Best regards
Mike Testro
Mike,
Many thanks for that.
How can I convert version 12 file into old version 10 ? any idea?
please reply.
Cheers
Hi Chris
Powerproject has a very simple filter system.
For critical activities you just select Float & Criticality in the filter drop down and then tick critical tasks - the default is zero float.
You then select the chart to show the critical activity.
Best regards
Mike Testro