Permanent Resource - Calendar, Working Time, Overtime

Hi all,

Is there a way to numerate total working time that a resource has been allocated, with separate figures for standard working time and overtime?

Currently I have a library of resources which i regularly use. I have duplicates of resources for those that work different calendars / times, but this is a bit disorganised and the library is oversized.

To solve this i was wondering if there was a way that you can allocate standard working hours to a resource, then when allocated to a task and if the task dictates the resource is required out of these standard hours this would be shown as overtime?

Chris

B
Ben Taunt 👤 Member for 14 years 4 months

Hi Chris,

I notice that you're using a fully supported licence of Asta Powerproject within your company - why not send this question directly to our support team so that they can help you?  They're committed to supplying a response within an hour so you'll get a faster turnaround that way:

UK Support Helpdesk: 01844 261609 or [email protected]

Best wishes,

Ben @ Asta

 

 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts