While progress line on a programme generated with Asta Power Project (APP) with v11 is @ 10/08/12. When file is saved as Primavera .xer and either re-opened in APP on in P6 V6.2, progress line/data date is changed to 24/03/12 which is actually the start of the project? What I should I be checlking?
Additionally, when programme either re-opened in APP on in P6 V6.2, start of in-progress activities are actualised in 2008/2009 and end dates brought back in?
Any ideas.
Hi Emmanuelle
The transfer between Asta and P6 is never perfect and small adjustments sometimes have to be made - particularly with calendars.
So i suggest you reset the progress line in P6 to the required date and check for any other peculiarities.
Best regards
Mike Testro