Hi All,

I have been tasked with creating a site staff resource programme by my employer.

I am relatively new to planning and am hoping someone could provide me with suggestions on how to efficiently create a programme for staff resources using ASTA.

The objective of the programme is to view working time against non productive time to assign excess capacity to jobs.

Any assistance would be greatly appreciated.

Thanks

Joe

M
Mike Testro 👤 Member for 20 years 6 months

Hi Joseph

Set up a series of task hammocks that contain the scope of work for each staff resource. For instance if you are employing an MEP supervisor then add all the MEP tasks to the hammock and then add the Supervisor resource to the hammock.

The same with other trades such as Groundworks - concrete - finishings etc.

Staff that are going to be on site full time add to the project Level 1 summary.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts