Hello,
How can I display cost centres conlumns in the spreadsheet? Can somebody please help me with this information?
How can I display one or more cost center columnn to see witch is the cost allocated on an activity for each cost center - manpower, matherial, plant, transportation, gas - defined in the project costs folder in the library?
Thank you!
Hi Dumitru
Right click on a column > open table definition > add a column > scroll down to Cost > open Cost box on the right > select the cost head or All if you have a lost of cost heads > apply & close.
Best regards
Mike Testro