Hide Activities in Asta

B
Bill Joshaf 👤 Member for 20 years 11 months
M
Mike Testro 👤 Member for 20 years 5 months

Hi Bill



In version 10 select the bar and right click on the task for the task drop down.



Left click on the "Mark for Hiding" option.



Repeat for all other tasks.



In the Format drop down click Hide Marked Items.



The marked tasks disapear.



Best regards



Mike Testro