Help on drawing bars

C
Christine P 👤 Member for 17 years 1 month
M
Mike Testro 👤 Member for 20 years 5 months

Hi Christina



As Paul wrote you do need to set the programme time units to minutes to get the results that you require - there is usually a drop down menu on the "Standard" icon menu.



Also make sure that the work pattern in your callendar does not have any Non-Work periods in the time zone that you are looking at.



Finally make sure that any resources attached to the task have the same calendar - this can be done in the modelling dialogue by ticking the "Calendar as Task" box.



There will be a full description of how to apply these items in the Help directory.



Best regards



Mike Testro

P
Paul Harris 👤 Member for 25 years 1 month

You need to change your snap Options. Do a search in help for snap and it will tell you all about it.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au

www.primavera.com.au

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts