Opening and closing a summary heading

B
Bo Johnsen 👤 Member for 20 years 3 months
M
Mike Testro 👤 Member for 20 years 5 months

Hi Bo



The double click is the quickest way to open/close a summary bar.



The + - column is when you are using "task per Line" mode with more that 1 activity on the same line.



This is very useful if you are doing repetetive tasks in different locations - Housing estates or High rise fit outs.



There are problems with Task per Line mode including



1. Cannot copy paste to the columns

2. Loss of criticality



Best regards



Mike Testro