How many id’s for each activity?

B
Bijaya Bajracharya 👤 Member for 21 years 3 months

Thank you for explaining. Graphics based and hence I had a feeling that Power Project would be more user friendly. But....

A
Andrew Pearce 👤 Member for 24 years 11 months

First of all you need to understand that power project is a graphically based programme.



You have bars Which are single activities on a gant chart line. As you add activities in your programme PP gives each one a line number (bar ID) at the same time PP allocates a unique ID to this bar, the unique ID does not change whereas the bar (or line no) changes if you add or move the bar.



In PP you have the ability to split bars into tasks and the same numbering logic applies to the tasks.



A way of checking this is to add columns to the spreadsheet for each token.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts