Del (pvt.) Ltd. Project Manager

1-Employer: – DEL (Pvt.) Ltd.



Project: – Lahore Ring Road Project-P15, Nov 01, 2009 – till date.

Construction of Interchange at

Bedian Road, Lahore.



Scope of Work: –

1.4 km Dual Carriageway, Service Roads, Ramps, Loops

Bridges, Subway, Underpass, Retaining Walls, Utility Culverts,

Drains, Water Courses & other road allied works.



Project Cost:- 2.14 Billion (PKR)



Designation :– Planning Manager



Job Responsibilities:-



•     Preparation of Site Mobilization Plan.

•     Preparation of Monthly Progress Reports.

•     Preparation of Weekly Progress Reports.

•     Preparation of Daily Progress Reports.

•     Preparation of Clause-14 Schedule.

•     Preparation of Level-V Schedule.

•     Incorporating Monthly Work Progress in Schedule & Preparation

Of Latest Forecast Schedules.

•     To generate 4-week and 3-month look ahead schedules.

•     Preparation of Material Requirement Plan.

•     Preparation of Manpower Requirement Plan/Histogram.

•     Preparation of Equipment Requirement Plan/Equipment Deployment Plan.

•     Allocation of Daily and weekly targets.

•     To generate earned v actual cost analysis reports.

•     Preparation of BCTC.

•     Preparation of Budget.

•     Preparation of comparative statements.

•     Preparation of Rate Analysis Sheets regarding subcontracting of

Work.

•     Preparation of Bottleneck Summary Report.

•     Analysis of Histogram, Critical Path and S-Curve.

•     Attending Monthly Work Progress Meetings with Client.

•     To keep an eye on work front availability.

•     To frequently visit project Site to facilitate in addressing problems/Issues.