From 2006 till 2008
Company: Assad Said Corp., Riyadh, KSA
Position: Project Manager
Projects done:
Name Of Project: Shuaibah IWPP Phase III 380 KV GIS Substation (Current Assignment)
Location: Shuaibah, Saudi Arabia
Main Contractor: Siemens
Scope: All architectural and civil works including but not limited to grading, excavation and filling, all leveling works, all earthworks, boundary fences and gates, Construction of Cast in Place Basement for GIS building and Foundations for Control Building and erection of 380 kv GIS Building and Control Building precast beams, columns, slabs etc including co-ordination ( Builders works) of HVAC, Small power & Lighting and fire fighting equipment, Cable ducts and trenches, all road crossings, electrical /fire fighting equipment foundations, all metal works, drainage & water supply systems, Plumbing etc.
Responsibility:
• Based on the construction drawings and contract documents prepare a detailed construction schedule.
• Direct and orient the workforce at site for smooth execution of project.
• Prepare various reports to successfully manage the project, such as: monthly
progress analysis / schedules, billings and status reports.
• Ensure compliance with contract requirements.
• Supervise documentation of all significant project events (e.g., accidents, delays, change orders).
• Direct pre-construction services and activities
• Maintain quality control
• Work collaboratively with head office management to ensure project is procured and constructed within the boundaries of the Company’s best practices while conforming to technical requirements.
• Manage the expediting of specialized manpower, materials, subcontracts and equipment.
• Organize schedules and working to tight deadlines.
• Responsible for completion of assigned projects within budget and schedule while meeting quality and safety goals of the company.
• Supervise the activities of all project activities including determining schedules, schedule of values, subcontractor selection, and submittal approvals.
Name Of Project: Access Road To Riyadh Cement Factory
Location: Nissah Road, Riyadh Cement Factory
Client: Riyadh Cement Factory
Scope: Construction of road connecting Riyadh Cement Factory Wth Nissah Road, Involving approximately 400,000 M3 of hard rock cutting (Cutting depth varying from 5 meters to 25 meters), 120,000 M3 of filling (Height of embankment ranging from 3 meters to 8 meters),Asphalting and associated Electrical works.
3) From 2005 till 2006
Company: Assad Said Corp., Riyadh, KSA
Position: Site Manager
Name Of Project: 132/13.8 kV Substation # 8115
Location: Al Badeea, Riyadh, KSA
Main Contractor: NCC/ Saudi Electric Company
Scope: Complete Civil & Electromechanical Works
4) From 2002 till 2005
Company: Assad Said Corp., Riyadh, KSA
Position: Planning Engineer
Projects done:
Name Of Project: Jubail Go Generation Plant
Location: Jubail Industrial City, KSA
Main Contractor: Siemens
Scope: Complete Civil Works for the Power Plant
Name Of Project: 132/13.8 kv Substation # 8821
Location: Buraidah, KSA
Main Contractor: Kadi
Scope: Complete Civil Works
Name Of Project: Asir CPS Extension
Location: ASIR, KSA
Main Contractor: NCC
Scope: Complete Civil Works For the Power Plant
Name Of Project: Khurais Road Transmission Station Upgrade
Location: Khurais Road
Main Contractor: Detecon/ Ministry Of Culture & information
Scope: Complete Civil and Electromechanical works
Name Of Project: Health Center Al Baha
Location: Al Baha, KSA
Main Contractor: Ministry of Interior
Scope: Complete Civil & Electromechanical Works
Name Of Project: Health Center Jizan
Location: Jizan, KSA
Main Contractor: Ministry of Interior
Scope: Complete Civil & Electromechanical Works
JOB DESCRIPTION:
1. Coordinate with all concerned Engineers, Client, and Managers in order to
formulate a Master plan of a project.
2. Establish and develop master schedules including procurement schedules.
3. Monitor overall progress of the project, actual vs plan forecast to
completion
4. Prepare project cash flow, actual vs. plan and forecasts.
5. Coordinate with all concerned discipline Engineers to design WBS and
utilizing it to develop project program using Primavera.
6. Establish and develop a baseline work program.
7. Monitor progress on daily basis.
8. Coordinate with the Procurement Manager and other concerned to establish
material Procurement schedule.
9. Arrange Monthly Progress Report, recommend changes and
Improvements.
This report is to include the following:
Summary of Activities
Areas of concern
Project Milestone
Shop Drawings
Description of construction activities
Engineering status
Procurement status
Construction status
Resources