ETA - ASCON GROUP Planner

•     Reviewing and Evaluating the construction drawings status and procurement status in preparation of schedules for project.

•     Develop and maintain realistic construction project schedules Level 4 for Mechanical, Electrical, and Piping activities.

•     Conduct regular site inspection for daily progress report and update Level 4 schedules for procurement and construction status.

•     Update daily progress on site for each activity by updating actual start date and finish date in each activity in Primavera Project schedule.

•     Prepare consolidated weekly and monthly progress reports such as s-curves, planned versus actual progress using Primavera Project Planner and Microsoft Excel 2003.

•     Monitor project cost and schedule performance, including calculation of cost and schedule performance indices.

•     Attend weekly meeting with the main contractor to discuss sequence of work items, time frames and windows to be accomplished.