Nippon Steel Senior Planner

South Sumatra - West Java (SSWJ) 32" Offshore Gas Pipeline Project - CP2.



- Preparing schedule and pipe loading scenarios to be implemented in relation to daily single joint welding productivity and barge window of availability using P5;



- Preparing transport barges schedule and sequences related to number of available barges and required traffic arrangement during pipelaying activity;



- Preparing pipes coating and thickness identification report;



- Preparing installed pipe joints identification report. Preparing returned pipes/ surplus construction material report;



- Preparing pipes delivery status report for each material barges sent from load-out yard;

- Preparing periodic progress report regarding construction activities including but not limited to: Near Shore Pre-trenching Works, Offshore Pipelaying Work and Post-trenching Works;



- Preparing weekly EPC and Overall Progress Report from MDR, Procurement Status Report and Construction Daily Progress Report;



- Preparing Project Coordination weekly Minutes of Meeting. Preparing weekly internal Minutes of Meeting;