Duties and Responsibilities:

Tender Stage:

Involved in preparation of the tender documents required such as:

o     Tender Program

o     Manpower Resource Schedule

o     Equipment Utilization Schedule

o     Traffic Management Plan

o     Construction Program of Works



Pre-Construction Stage:

Involved in preparation and review of contract requirements such as:

o     Construction Program (Clause 14.1 of FIDIC)

o     Conditions of Contract for Works using FEDERATION INTERNATIONALE DES INGENIEURS CONSEILS STANDARDS (FIDIC)

o     Construction Methodology

o     Contract Drawings and Specifications









Construction Stage:



o     Reports directly to British Construction Manager

o     Planning and scheduling (computer aided) e.g. work breakdown structuring, resource loading and productivity analysis, progress monitoring and coordination, critical path analysis, look ahead schedules)

o     Responsible for the day-to-day preparation and monitoring of the technical documentation of the project.

o     Prepares construction method statements, traffic management plan and other technical submission required for the project.

o     Attends progress meetings with subcontractor