Planner

Shut Down Projects (Reliance Industries Ltd., Refinery Division Jamnagar)

Company     : - G.R. Engineering works Pvt. Ltd., Mumbai.

Quality Yield improvement – 1 Dec. 2003 in VGO /DHT/Coker Unit.

1. Planned & Managed with coordinators for shutdown project.

2. Coordinated Teams of Engineers Designers, Technicians & Performed Scheduling, and Job estimation & completed the projects before prescribed schedule.

3. Nozzles modification / addition from (2” – 30”, straight, tangential, self reinforced (dollar plate), Skirt Nozzles, Clad Nozzles) on main fractionators, column, stripper, vessel.

4. Demister rings, sparger rings, coalascers, internal works in vessel & columns.

5. Structural work including platform erection, platform cleats welding, (on alloy steel & Low carbon steel).

6. Quality stage wise Inspections with M/S. KOTCH GLITSCH, England, and REAL QMD