GATE Construction (Gama– Tekfen Partnership); Planning Engineer responsible for developing contract programme into detailed working programme consisting of such site activities as construction of concrete&steel structured buildings/piperacks & their detailed finishes, infrastructures, prefabrication & installation of oil & gas process piping, mechanical equipment erections, power plant specific electrical installations and monitoring performance & productivity of these site activites&gangs via earned value analyses, producing & presenting extension of time claims, getting agreed on revised contract programme, disruption claims, time & time related cost impacts of variations, contract & subcontract administration works for Kashagan Field Development, Power Generation Plant Project in Atyrau/Kazakhstan.