Limak construction CO Senior Planner

Project:

Emergency rehabilitation of Kabul - Salang - Doshi Road project, (Section 2, Olang - Doshi section), including bridges and tunnels, Total 75 km, 2 lane highway re-design, and construction activities. Total $29.6 M. USAID funded, supervised by Louis Berger Group of USA as a consultant.



Responsibilities: (Reporting to Project Manager)

•     Preparing daily, monthly progress reports,

•     Preparing progress certificates and submitting to consultant,

•     Coordinating the procurement activities,

•     Controlling subcontractors progress certificates,

•     Planning necessary man power, materials, machineries and equipments,

•     Preparation and updating the construction Schedule, dynamic scheduling,

•     Participating into progress meetings,

•     Slippage reporting and taking necessary measures to complete the work on time.

•     Solving the technical problems with the management & with the supervisor,

•     Monitoring the Material tests,

•     Preparing the required procedures,

•     Preparing the claims according to FIDIC,

•     Reviewing EOT claims and related Cost claims,

•     Preparing counter arguments against engineers` claims,

•     Developing strategies for substantiating EoT and cost claims through contractual and technical arguments,

•     Coordinating issues with consultant for solving any dispute in quantities,

•     Evaluating Variation Orders,

•     Evaluating final quantities,

•     Participating in negotiations with the Engineer concerning EoT and cost,

•     Contract administration,

•     Following-up the amendments,

•     Outgoing and incoming letter management,

•     Controlling of the shop drawings, (and other Document Controlling activities),

•     Controlling the asphalt plant productivity,

•     Performing Rate analysis for the new items,

•     Sifting and compiling contemporary records constituting evidence for the claimed time and cost.