Hello All,
Need advise.
I am now on a Project which was started in Jan 2022 but was stopped in Oct 22, but now will be starting again in Jul 23.
Many activities have started, but not completed.
How to reschedule it.
Please provide me options/opinion.
Thanks
Jithin
If work stoppage applies to a few activities then copy the activities calendars to new calendars, apply the exception to the new calendars and assign to these activities and affected lags.
Anyway, until a new directive or change order mandates something else you have no option than delay what is still under the contract.
Scheduling Work Stoppage might require a few adjustments, among others:
https://www.eastwoodharris.com/DL/TP/201030_p6_elapsed_duration_activities.pdf
I use Spider Project but any scheduling software shall do it.
Good Luck