Global Claim versus time-slice one?

A
Andrew Flowerdew 👤 Member for 21 years 5 months

Everyone seems in agreement, generally any claim needs to be substantiated in terms of cause and effect to the highest degree that the available information will allow.



Global claims are not acceptable if it is possible to break down the claim into smaller parts.

S
Shahzad Munawar 👤 Member for 22 years 11 months

I totally agree with Uri that Global claims may not taken into account with respect to its proven substantiation.



Such claims may be accounted for when the Employer wants to settle the claims globally to cover both sides defaults amicably i.e Contractor and Employer.

U
Uri Shachar 👤 Member for 23 years

Daniel,



The only situation in which it would be better for the Contractor to make a ’Global’ delay claim is when he can not properly substantiate a more accurate analysis. Remember: time slices is only one technique, there are other techniques that might be more suitable, depending on the merits of each case).



Disruption claims (as opposed to delay claims) may sometimes be based on ’Gloabl’ analysis if no better alternative can be found.



Generally speaking, Gloabal claims are very difficult to prove, as establishing ’Cause and Effect’ which is important in delay analysis claims is problematic.



Try to avoid ’Global’ claims.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts