Hook Time Analysis

Member for

19 years 10 months

Hi Paddy
I have a paper on Hook Time based on Asta PowerProject.
PM me with an email and I will send it to you.
Best regards
Mike T.

Member for

24 years 9 months

The best tool to use is a Multi-Activity Chart to work out key cycle times then its a process of extrapolating the cycle times to various quantities and looking at alternatives (eg, using a pump instead of a crane for lifting concrete).  Multi-Activity Charts are described at: https://www.mosaicprojects.com.au/WhitePapers/WP1025_Multi-Activity_Charts.pdf

Member for

7 years 3 months

 My other question would be is there a basic formula to work out the number of lifts required per day from the tonnage of steel in each wall/base.

 

I seen something on another thread for tower cranes tha had an example:

Maerial Type    Volume     Container    Capacity   Hooks  Programme Tasks   Hour per day  work day  hook per day

Rebar in slab     69T          Sling            1.2          58             5                           12             3               4  

 

I was wondering what the work day value was and how that relates to hook per day

Member for

14 years 5 months

I'm no expert on high rise but it would be worth speaking to the crane hirer and manufacturer.To get a good balance, I would speak to manufacturers of similiar capacity machines too.Let me know how you get on