Hook Time Analysis

Hi All

 

I am currently working on tendering for a job which will use a 160T crane. My problem is ( New to the tendering game) i am struggling to work out what the hook time is and if we require 2 cranes for the duration of the job, Production percentages etc

 

Is there a excel spreadsheet or any examples that somone could help me with?  How would i work out the hook time etc

M
Mike Testro 👤 Member for 20 years 5 months

Hi Paddy
I have a paper on Hook Time based on Asta PowerProject.
PM me with an email and I will send it to you.
Best regards
Mike T.

P
Paddy Doherty 👤 Member for 7 years 10 months

 My other question would be is there a basic formula to work out the number of lifts required per day from the tonnage of steel in each wall/base.

 

I seen something on another thread for tower cranes tha had an example:

Maerial Type    Volume     Container    Capacity   Hooks  Programme Tasks   Hour per day  work day  hook per day

Rebar in slab     69T          Sling            1.2          58             5                           12             3               4  

 

I was wondering what the work day value was and how that relates to hook per day

M
Mark Hogan 👤 Member for 15 years

I'm no expert on high rise but it would be worth speaking to the crane hirer and manufacturer.To get a good balance, I would speak to manufacturers of similiar capacity machines too.Let me know how you get on

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts