Dear, I have intentionally allow more time in the early stage of the programme in order to avoid early warning from the architect if there is any delay, and more tight schedule at the later stage. The progress is actually delayed at the early stage due to non possession of some area due to the default of the architect, however, after the completion up to 3/F, the progress had caught up according to the master programme. Then, the architect claim that no EOT will be granted as all the delay has been caught up. i.e. the client had taken all the float in the early stage and put main contractor in a very unfavourable condition. Is the architect correct? Regards, Gary Lo
Float in programme
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
I suggest in the future showing some terminal float as suggested [REQUIRED] by NEC3. In such case early activities would be tight as well as late activities. No warning shall be issued for consumption of available terminal float, it is yours!
If early critical activities are delayed by contractor then contractor terminal float is reduced because of contractor actions and no EOT is granted, if early critical activities are delayed by cause of client action terminal float is consumed and cannot be used to mitigate the effect of a compensation event.
Terminal float is a basic requirement to increase probabilities of success in project risk analysis. Not allowing for terminal float and require schedule not to show some early planned completion is self-defeating, is poor planning practice, to the point NEC3 requires all plans to show some terminal float.
http://www.stevencevans.com/float/
Generally, there are 3 types of float:
As a general principle, NEC3 deals with each as follows:
It is important to remember that all the above must be shown on the Contractor’s programme and a failure to show it is a reason for the Project Manager to refuse to accept it.
Hi Gary.
Yes the Architect is correct.
Serves you right for manipulating the programme.
Best regards
Mike Testro