I am looking to add the project weeks to the top line in the date zone properties so that I can quickly see which weeks have elapsed. At present it is set to days. How do I amend this to weeks?
Thanks
I am looking to add the project weeks to the top line in the date zone properties so that I can quickly see which weeks have elapsed. At present it is set to days. How do I amend this to weeks?
Thanks
Hi Dominic,
Right-click on the date zone and go to Properties. If you have project days showing already, this line will have the type set to elapsed units with the time unit set to elapsed day. Simply change where is says elapsed day to elapsed week!
If you need to add in an extra line, change one of the unused lines to elapsed unit and elapsed week.
For further assistance, take a look at the date zone topic in the help file.
Thanks,
Ben @ Asta Powerproject