Why "Fragnet"

M
Mike Testro 👤 Member for 20 years 5 months

Good Morning Analysts

I dislike the term "Fragnet" used by some analysts to describe a series of events inserted into a barchart to represent delaying events.

Why Fragnet - is it supposed to a connection of "Fragmented Network"? If so then why so?

I suspect that the term is meant to make the analysts art even darker - in which case it should be banned.

I agree that the process is sound which is why I place the delaying events into a Sub-Chart - even a Judge can understand that plain English.

Best regards

Mike Testro

A
Anders Axelson 👤 Member for 22 years 6 months

Mike,

It's (originally) a US term, meaning fragment of a network. I believe it was first used in the 1960s or thereabouts, in the context of using hand-drawn networks to present extension of time claims (this was after CPM had been invented but before PCs). It is cumbersome to reproduce a network fully by hand, so only the relevant fragment of it would be reproduced in presenting EOT claims. Change could be mapped by hand by superimposing a fragnet on a network using tracing paper, or using a red pen, or something like that. The term 'fragnet' I believe entered the public domain when an analysis technique employing fragnets was cited with approval in a US Federal Board of Contract Appeals case (don't ask me which one) in the late 1960s or early 1970s. With that judicial approval the term became more widely adopted.

I wouldn't read too much into Primavera's use of the term, from the 1980s onwards. The Primavera developers, I imagine, decided to add a new feature so that users could save only a part or section of a project. They would have used the term "fragnet", I guess, because it was a sexier sounding buzzword than "part" or "section".

M
Mike Testro 👤 Member for 20 years 5 months

Hi Alexandre

Thanks for the explanation - It is as I suspected - a primavera addition to planning language.

More proof - if it is needed - that they are taking over the world of planning.

Best regards

Mike Testro

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hi Mike,

I know "fragnet" as a Primavera Project Planner (P3) library of activities that I can insert in a project to make the process of building the project plan easier.

The same process does exist in SpiderProject under the name "Typical Fragment" and in PowerProject or Tilos as "Tasks Groups"

Best regards,

Alexandre

Forum Sponsor

Top Posters

henrigpc
0 posts
Hashil Ali
0 posts
Nigel Hussey
1 posts
James Williams
74 posts
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts