BL1 Total Float Calculation Issues

Member for

17 years 8 months

The dates used to show after the baseline is saved is PLANNED START and PLANNED FINISH of the baseline schedule, so I am thinking the reason may be the planned dates are not exactly same with current dates in your current schedule, and the TF will be different as it calculated with planned dates I guess.

The way to resolve it is to show planned start and planned finish column in the activity table and compare with current dates, copy to excel may be quicker I think.