Site Instructions Vs. Variation Orders in Assessing EOT

D
Dimple Dean 👤 Member for 10 years 7 months

Hi All!

I am working on a Client side, I have a project scenario as below.

1.       In our project, the conditions of contract states that Contractor cannot proceed without the approval of V.O.

2.       Site Instructions has issued to Contractor before the approval of V.O. and on actual Contractor started V.O. works on site before the V.O. was approved by Client.

Now my question is, in analyzing delays using any method or TIA, what date must be used by us as a Client? Is it the date the V.O. was approved or is it the date Contractor has started on site based on the procurement and delivery dates?

 

Thanks in advance!

M
Mike Testro 👤 Member for 20 years 5 months

Hi Dimple

The daily report is a statement of fact so use it.

Best regards

Mike T.

D
Dimple Dean 👤 Member for 10 years 7 months

In considering the start date of work, is it the date from the Daily Report or I can use the Delivery Date of the materials?

Many thanks Mr. Mike

 

M
Mike Testro 👤 Member for 20 years 5 months

Hi Dimple

The contractor has proceeded with the variation at risk of receiving a VO. He has in fact mitigated the impact of the delay.

The piece of paper is only retrospective confirmation of something that has happened.

The date of impact of the event therefore must be the date that the Contractor started the work - it seems unfair but that is the case.

Apply the rules but please do not unjustly punish a contractor who was only doing his best.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts