Forensic Claims Analysis Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Fri, 2015-11-27 13:54 Permalink Hi DimpleThe daily report is Hi Dimple The daily report is a statement of fact so use it. Best regards Mike T. Member for 10 years Member for 10 years Submitted by Dimple on Wed, 2015-11-25 18:42 Permalink In considering the start date In considering the start date of work, is it the date from the Daily Report or I can use the Delivery Date of the materials? Many thanks Mr. Mike Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Tue, 2015-11-24 21:49 Permalink Hi DimpleThe contractor has Hi Dimple The contractor has proceeded with the variation at risk of receiving a VO. He has in fact mitigated the impact of the delay. The piece of paper is only retrospective confirmation of something that has happened. The date of impact of the event therefore must be the date that the Contractor started the work - it seems unfair but that is the case. Apply the rules but please do not unjustly punish a contractor who was only doing his best. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Fri, 2015-11-27 13:54 Permalink Hi DimpleThe daily report is Hi Dimple The daily report is a statement of fact so use it. Best regards Mike T.
Member for 10 years Member for 10 years Submitted by Dimple on Wed, 2015-11-25 18:42 Permalink In considering the start date In considering the start date of work, is it the date from the Daily Report or I can use the Delivery Date of the materials? Many thanks Mr. Mike
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Tue, 2015-11-24 21:49 Permalink Hi DimpleThe contractor has Hi Dimple The contractor has proceeded with the variation at risk of receiving a VO. He has in fact mitigated the impact of the delay. The piece of paper is only retrospective confirmation of something that has happened. The date of impact of the event therefore must be the date that the Contractor started the work - it seems unfair but that is the case. Apply the rules but please do not unjustly punish a contractor who was only doing his best. Best regards Mike Testro
Member for
19 years 10 monthsHi DimpleThe daily report is
Hi Dimple
The daily report is a statement of fact so use it.
Best regards
Mike T.
Member for
10 yearsIn considering the start date
In considering the start date of work, is it the date from the Daily Report or I can use the Delivery Date of the materials?
Many thanks Mr. Mike
Member for
19 years 10 monthsHi DimpleThe contractor has
Hi Dimple
The contractor has proceeded with the variation at risk of receiving a VO. He has in fact mitigated the impact of the delay.
The piece of paper is only retrospective confirmation of something that has happened.
The date of impact of the event therefore must be the date that the Contractor started the work - it seems unfair but that is the case.
Apply the rules but please do not unjustly punish a contractor who was only doing his best.
Best regards
Mike Testro