The answer is simple, when you export, use the DBF format ( Database files) for your files, Excel has no problem in openining them. Make sure you choose the right fields. The ID field (ACT) is always important, and I always make sure I export the descriptions as well ( you can delete them before importing), but it helps in doing a random check.
The reason I use DBF is that P3 is more user friendly to DBF files as the program has a database driver. Howevever, if you make major changes to DBF files in EXCEL, open a new spreadsheet, and make sure it has only one page, then copy the data to this spreadsheet, and save it as a .DBF file.
Make sure you do not try and import fields that contain unwanted info, so it is important to understand what fields contain what, by their abreviated names. I suggest the HELP" files as they give the various fields names.
Member for
20 years 11 monthsRE: Import Actual Hours in P3
Hi Steve,
The answer is simple, when you export, use the DBF format ( Database files) for your files, Excel has no problem in openining them. Make sure you choose the right fields. The ID field (ACT) is always important, and I always make sure I export the descriptions as well ( you can delete them before importing), but it helps in doing a random check.
The reason I use DBF is that P3 is more user friendly to DBF files as the program has a database driver. Howevever, if you make major changes to DBF files in EXCEL, open a new spreadsheet, and make sure it has only one page, then copy the data to this spreadsheet, and save it as a .DBF file.
Make sure you do not try and import fields that contain unwanted info, so it is important to understand what fields contain what, by their abreviated names. I suggest the HELP" files as they give the various fields names.
Hope this is of assistance.
Regards
Philip
Member for
24 years 6 monthsRE: Import Actual Hours in P3
You will need toad the Resource ID to update resources.
When you have multiple resources per activity you will export a line per resource, thus producing a unique identifier for each resource.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
www.eh.com.au
Member for
22 years 11 monthsRE: Import Actual Hours in P3
That data is held not at activity level, but at resource level. You would need to export/import resource-wise.
HTH