Import Actual Hours in P3

Member for

20 years 11 months

Hi Steve,



The answer is simple, when you export, use the DBF format ( Database files) for your files, Excel has no problem in openining them. Make sure you choose the right fields. The ID field (ACT) is always important, and I always make sure I export the descriptions as well ( you can delete them before importing), but it helps in doing a random check.



The reason I use DBF is that P3 is more user friendly to DBF files as the program has a database driver. Howevever, if you make major changes to DBF files in EXCEL, open a new spreadsheet, and make sure it has only one page, then copy the data to this spreadsheet, and save it as a .DBF file.



Make sure you do not try and import fields that contain unwanted info, so it is important to understand what fields contain what, by their abreviated names. I suggest the ’HELP" files as they give the various fields names.



Hope this is of assistance.



Regards



Philip

Member for

24 years 6 months

You will need toad the Resource ID to update resources.



When you have multiple resources per activity you will export a line per resource, thus producing a unique identifier for each resource.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Book Publishers, Training & Consulting

www.eh.com.au

Member for

22 years 11 months

That data is held not at activity level, but at resource level. You would need to export/import resource-wise.





HTH