Adding Indirect Cost Through Primavera

I've recently started Working as a Planning Engineer and I am currently working on a project for which I have done Scheduling, Resource Scheduling and Costing for that Project But I am stuck in one thing that is our work is done in remote areas and we provide facilities to our manpower like Transportation allowances,Food Allowances,Daily transportation From camp to Site, accommodation.I want to add there costs in my project and show them Separately. Any Suggestions Would be appreciated.

J
Johannes Vandenberg 👤 Member for 16 years 4 months

Hi Ammar

I suggest to use the "expenses" facility and enter these in a WBS summary at the location you see the most fit.

Regards Johannes

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts