Planned % Complete vs. Actual % complete

Member for

14 years 1 month

Hi Shannon,

 

as Rafael already mentioned you have to have a copy of your project that you must progress 'as planned'

When you add this copy to your real schedule as a baseline you can add a 'baseline percentage complete' column to your lay out.

Regards,

Arend

Member for

21 years 8 months

I am not a P6 user but I would consider the following.

1- Create an updated as planned baseline schedule - from baseline, to the data date of the updated schedule as if occurred as planned. In this way you will get planned values of every line item.

2- Set updated as planned baseline as your comparison job.

3- Display desired values on your updated schedule with actual progress versus the comparison job [an updated baseline progressed as planned].

Suggest creating a UDF to record the planned values using global change. In this way you can compare to other baselines and still be able to display these values.

Displaying the planned values for every line item is not as easy as comparing progress curves, it requires some extra homework.

Good luck,

Rafael

Member for

13 years 9 months

 

Planned % Complete is represented by Schedule % Complete, your programme should be loaded with resources and cost in order to generate the total Planned % Complete at the highest level, Actual % Complete is equal to Performance % Complete.

Hope it helps... 

Member for

19 years 1 month

you update your baseline (you can do it automatically), and then show your baseline % complete