As late as possible constraint

Member for

11 years 5 months

Dear sir

You can create a new tasks and apply base line for that task and then you have to give constriant as late as possible now we see the difference

Member for

19 years 10 months

Hi John

If the milestone is for the commencement of design then there must be a duration for design completion.

This should be expressed as a task bar and linked FS to the task or milestone that requires the design input.

Remove the lag and set the design task to ALAP.

You can then monitor progress on the design task.

Best regards

Mike Testro 

Member for

14 years 3 months

Guys,

Thanks for taking the time to reply.

I agree with what you guys have said in that there is nothing wrong with ALAP constraints when used correctly, good example Gary on the M&E equipment.

The activities in question on my analysis are commencement of Design activities for various parts of the Project.  These activities have no Predecessor and the only reason i can assume for using ALAP on the commencement of Design activities is possibly due to lack of Design resource.

 

I have removed the ALAP constraints and linked the said activities to the NTP milestone with positive lag ensuring no change in dates etc, this means as i import progress to my baseline as i proceed with my Windows analysis that these activities will remain in the same date unless progressed. Should i have left the ALAP constraint and just linked to the NTP milestone with lag? i think by removing the ALAP milestone i will start getting some spurious results, ie said activites being identified as the cause of delay when i reality it isn't.

 

Thanks

Member for

16 years 7 months

Nohing wrong with using ALAP in the right circumstances, as Mike & Vladimir have said.

I would add though that just because an ALAP constraint is appropriate does not mean having no predecessor is, even if the predecessor is not (currently) driving the activity.

Eg delivery of M&E equipment to site may be on an ALAP, so you do not have it sitting around on site for months before the civils are completed to allow it to install. But you should still have a design/procurement predecessor chain.

Client free-issues may have a project design predecessor, or if not should at least be linked from contract award.

 

Member for

19 years 10 months

Hi John

Vladimir is right - use of ALAP tasks such as "Last Date for Power On" or "Employer Free Issue Material On Site" is the natural way to set a task that has no predecessor in the programme but depends on outside influences.

If an event delays such tasks the in a delay analysis I would insert a bar that represents the delay period immediately before the ALAP task and hold that with a Must Start On constraint - then reschedule.

I would then colour the delay event bright scarlet but you can't do that in P6.

Best regards

Mike Testro

Member for

24 years 8 months

Why?

If you plan JIT supplies, training before implementation, etc. ALAP is very useful, practical and natural.

Member for

13 years 7 months

John,

I'd try to eliminate the ALAP contraints by talking to the relevant subject matter experts in the project team about the activities concerned, requesting that the SMEs define the predecessor activities so that finish-to-start logic can be used instead.

Neil