Predecessor & Successor GOTO Button

Member for

22 years 9 months

Nicolas,

F5 is the shortkey for Edit, GoTo; Ctrl+G is the French equivalent to the English Ctrl+B (Gras versus Bold)

the original question was not how to go to a specified task, but how to go to the current task predecessor or successor

Alexandre

Member for

18 years 4 months

Hi, all!



I am very much surprised that no one here

and especially you Alexandre,

mentioned the {F5} key.



All you have to do then is type the task number and hit {Enter}

and zou you are there!



Btw, in the French version of MSP 2k3,

{Ctrl}G modifies the grease of the text.

Member for

20 years 7 months

Hi, Alexandre!



Sorry to hear that the pre-requisites are a problem for you. I assume you determined this from the trouble-shooting guide at:



http://www.sumatra.com/projectoptimizer/troubleshoot.htm



It installed effortlessly on my machine, and no one else has mentioned having problems with it. But then I run primarily Microsoft software. Since all the pre-requisites are Microsoft, I guess most people (like myself) who use MS Project already have the pre-requisites set up.



I do think it’s extremely useful software, especially when your project slips and you are looking to compress schedule. Two suggestions I can make:



(1) Try Vladimir Liberzon’s Spider Project, which also computes DRAG.



(2) Compute it manually. This is quite difficult on large projects with lags and complex (SS, FF, SF) dependencies. But it’s not too hard on smaller projects (under 200 tasks) with only FS relationships. If it helps, the general rules for computing DRAG in such networks is:



1. DRAG is ONLY on critical path tasks.

2. If a CP task has NOTHING in parallel, its DRAG is its duration.

3. If a task DOES have other tasks in parallel, its DRAG = whichever is less: its duration OR the total slack of the parallel task with the LEAST total slack.



(For all the above, the definition of a parallel task is any task which is neither an ancestor nor a descendant of the specific CP task.)



Obviously, figuring out the DRAG becomes a bit tricky as the network gets larger and more complex. On the other hand, figuring it out "in your head" also can be lots of fun -- sorta like a Sudoku puzzle!



Fraternally in project management,



Steve the Bajan

Member for

22 years 9 months

Stephen,

ProjectOptimizer is certainly something useful; would be much better if it was willing to install on my PC

the pre-requisite list of items is so long! one more software I will never use, I do not want to spoil my working environment to try it

Alexandre

Member for

20 years 7 months

Hi, Dean.



Although Primavera is certainly a more robust system, there are some saving graces with MS Project. This is largely due to the fact that other companies write useful add-ons for MSP, but not for Primavera.



One functionality that seems related to your question is that of the Project Optimizer add-on from Sumatra.com. Your quest for to GOTO button suggests that you are attempting to optimize your schedule to a specific task. The Sumatra product will allow you to designate a specific mid-project task (one that may have lots of slack) and designate it as your sink activity. Then it will create a CSV file of a subset of the project consisting just of the targeted task and all of its ancestors (predecessors, but also predecessors of predecessors, and predecessors of... all the way back to the start, both driving and non-driving).



If you then import that CSV file back into MSP, you can use all the Project Optimizer functionality to determine any tasks performed out-of-sequence, and to compute the drags of all the tasks delaying the new critical path to your targeted activity. This is something that’s very useful for schedule optimization, and that no version of Primavera does (although Spider Project computes drag, also).



The Sumatra product only works with MSP 2007. You can download a free trial copy at:



http://sumatra.com/projectoptimizer/projectoptimizer.htm



(And no, I don’t have any financial arrangement with either Microsoft, Sumatra, or Spider Project!)



Fraternally in project management,



Steve the Bajan

Member for

17 years 9 months

Dean,



Anything up to and including 2k3 is a bit limited in that respect.



As Alexandre again correctly points out 2k7 has a Task Driver functionality that identifies the task or tasks that affecting the start date of whichever task is of interest.



There’s also multiple undos and the ability to track changes in 2k7, so best you migrate over tout suite. It might lower your blood pressure a little until you find your way back to Primavera ;o)



Regards,



Darren

Member for

19 years 7 months

We are on 2003 at the mo, but very soon going to 2007 (New contract / client etc.)



I will look out for this task inspector as soon as we get access.



Thanks,

Dean.

Member for

22 years 9 months

Dean,

which release of MSP are you working with?

MSP 2K7 introduced the "Task Inspector" functionality, that let you click on the driving predecessor

Alexandre

Member for

19 years 7 months

Hi Darren,



Yes I knew of the CTRL-G "Goto" function, but it gets worse than I thought. Not only can you not just goto the predecessor or successor of interest, but MSP does NOT give you any indication of which of these items is the driver or being driven by the current activity.



So not only do you NOT have the means of getting there, but it doesn’t tell you WHERE you should be going in the first place.



Thanks for the reply,

Dean.

Member for

17 years 9 months

Hi Dean,



Alexandre is correct, MS Project has a ’Go To’ function it’s just not very well publicised and a bit more mandronic than simply clicking a predecessor or successor button or hyperlink.



It takes a bit more time, but it’s not too onerous. The Form View (Split) always shows the IDs for predecessors and successors, so Ctrl+G and a bit of typing and you’re there.



Regards,



Darren

Member for

19 years 7 months

You are preaching to the converted Alexandre!



I already know this and I am not changing to MSP through choice.



Regards,

Dean.

Member for

22 years 9 months

Dean,

MSP is not and will never be P3 nor P6

MSP is a small poor thing as compared to Primavera’s apps.

Alexandre

Member for

19 years 7 months

Thanks Alexandre,



This is the answer I expected (and feared). I suspected that this facility was missing, but put it out there in the hope that I was wrong!



Regards,

Dean.

Member for

22 years 9 months

Dean,

do not waste your time, such a functionality does not exist in MSP; if you know the predecessor or successor number, you can use Edit, GoTo instead, but it is far less efficient.

Alexandre