Hi! I am newbie with this type of program and career line.

 

Please enlighten me with resources. They gave me a file with indicated budget for each activity and I need to make an s-curve using p6.

 

Is this possible?

 

Ex.

Activity ID Activity Name Orig Duration Start Finish   

   A1020     Excavation            180 05-Jan-19 03-Jul-19

Member for

19 years

Haresh,

This is common if you modify your resource rate or change something which is also affected by duration type setting. If both prices assigned to resource and activity detail, resource tab are the same then try this.

Tools-> Recalculate assigment Cost. That should fixed the problem.



Note: Things that needs to check

1) Edit-> User Preferences-> Time Units tab-> Unit Format (is it hour or day?)

2) Resource max unit/time = (8/day or 10/day)

3) Resource Price/ Unit = ($?/h or $?/d)

4) Activity Window-> Resource tab-> Budget Unit = ?

5) Activity Window-> Resource tab-> Price/unit = ($?/h or $?/d)

Member for

16 years 3 months

Hi,



Joel is correct refresh ur data or check ur Admin Preferences may be something wrong there......!



regards,,,,,


Member for

19 years 2 months

Dear Mr. Joel,



Both prices assigned to resource and activity detail, resource tab are the same.



But still the problem persists



regards,



Haresh