Oracle Primavera - PM6 Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Tue, 2010-04-06 10:45 Permalink RE: Cost Accounts Sophia, Yes you can assign multiple cost account in Activity. Cost account is assigned on resources assigned to activity which can be different cost account on each. Log in or register to post comments
Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Tue, 2010-04-06 10:45 Permalink RE: Cost Accounts Sophia, Yes you can assign multiple cost account in Activity. Cost account is assigned on resources assigned to activity which can be different cost account on each.
Member for
19 yearsRE: Cost Accounts
Sophia,
Yes you can assign multiple cost account in Activity. Cost account is assigned on resources assigned to activity which can be different cost account on each.