Oracle Primavera - PM6 Member for 16 years 5 months Member for 16 years 5 months Submitted by ROHIT RANGNEKAR on Sat, 2009-06-06 05:28 Permalink RE: WBS Thanx sir Member for 18 years 6 months Member for 18 years 6 months Submitted by Arnold Puy on Sat, 2009-06-06 05:25 Permalink RE: WBS Hi Rohit, Unfortunately No. Because the WBS always start with the Project ID and followed by the WBS Code. The only way is to change your Project ID into T1 and input manually the WBS Code A,B.....C. Regards, Arnold Log in or register to post comments
Member for 16 years 5 months Member for 16 years 5 months Submitted by ROHIT RANGNEKAR on Sat, 2009-06-06 05:28 Permalink RE: WBS Thanx sir
Member for 18 years 6 months Member for 18 years 6 months Submitted by Arnold Puy on Sat, 2009-06-06 05:25 Permalink RE: WBS Hi Rohit, Unfortunately No. Because the WBS always start with the Project ID and followed by the WBS Code. The only way is to change your Project ID into T1 and input manually the WBS Code A,B.....C. Regards, Arnold
Member for
16 years 5 monthsRE: WBS
Thanx sir
Member for
18 years 6 monthsRE: WBS
Hi Rohit,
Unfortunately No. Because the WBS always start with the Project ID and followed by the WBS Code.
The only way is to change your Project ID into T1 and input manually the WBS Code A,B.....C.
Regards,
Arnold