S-Curve Shape

A
Ali Hamouda 👤 Member for 24 years 4 months
A
Ali Hamouda 👤 Member for 24 years 4 months

Hi,



thank you for your time.



If it is possible to see example of this calculations in excel sheet,would be appreciated.



my email: [email protected]



Ali Hamouda

==========================================

L
Luca Basile 👤 Member for 22 years 11 months

As mentioned by Alex, divide Your work in smallest work packages, for each work packge go more in detail up to your control level (is an engineering or construction project or better and EPC).

Load all the activities with man-hours, costs, then use toold graphic function of P3 and make the hystogram of the costs (bar and cumulative) You will have your S-curve, based on cost, good also for further EVA analysis.

If You want to make it in excel use instead tool report, generate the report in csv, so you can easly make the chart.

What You were telling us about percentage at certain time of the project, You can put some milestone in Your project at their achievement. So if You are sure of the logic, see the group of works that is giving your required percentage and then put a milestone at their end, so You can also easily monitor if You will be in delay or ahead.

A
Alex Wong 👤 Member for 23 years 4 months

Amazing how you came up with your s-curve



IMHO the reason why the S-Curve is S shape is due to the nature of the work breakdown sturture (WBS) if you only have one activity per project yes you can use the resource distribution curve to drive your s-curve shape. However, as a planner you have to divid your works into a smaller manageable size of activities and load them with the corresponding % of work load then schedule them into the right time and logic. And that is how you obtain your resource curve. It may vary from project to project but it is a lot accurate than one activity with a res dist. curve.


F
Forum Guest 👤 Member for 17 years 4 months

For the purpose of Planned Values.



we have to maintain a certain percenatges when we start to cost load the project



at the first 3 monthes we have to get 12.5% and the 2nd quarter we will get 50% at the following quarter we will get 75% at the end we will get 100 %..



this percenages will lead to a bill or like S-shape curve.



any comment will be appreciated



thanks

Ali

#########################################

F
Forum Guest 👤 Member for 17 years 4 months

If you consider that a curve is generated by cost(or quantity) values from each individual activity, being distributed between the Early (or Late) dates of an activity, then the "shape" of the curve is dictated by the distribution of such cost(or quantity) values, whatever shape that takes. And enforcing a standard "shape" is, IMHO wholly incorrect.

M
MK TSE 👤 Member for 24 years 3 months

Consider a bell shape distribution to each item which can be distributed throughout the project.

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts