As your project is not even at the "questimate stage" any number chucked into the ring is as good as the next.
At at this stage of the work, your two educated quesses are the best you can do untill you can get some lower level estimating/costing organised.
Try basing the camp size and its services on an average of your two numbers, spread out equally over all the projects, then as the estimates develope update your original number. Its the best that can be achieved at this stage of the project.
But at the same make sure the layout and area of the camp / services can be easily changed modified to reflect increases / degreases in numbers etc.
It never ceases to amaze once we planners have "developed" a number, others will start to produce their numbers and so the estimate will clarify etc, but make sure your management understand what your numbers are based on and how they have been developed:- (its called diping hands in the blood).
Regards
John L.
Member for
24 years 5 months
Member for24 years5 months
Submitted by Richard Beazley on Wed, 2007-12-12 05:59
Appreciate your quick response! And you are absolutely right. The reality is that we are the Project Management Contractors/Consultants. The client, who has all the estimators, cost engineers etc have given us no information at all, though we do have rough figures for total budget.
They have no plans to give us the schedule because it is not firm enough to plan with...!! Again we have a very rough one page schedule, which has been overtaken by events. Each of the projects has a completely different sponsor, financing arrangements etc. Its going to be challenging to say the least! They are working on estimates and the minute I have those I can work it out!
I guess I need to search our archives and dig out data from similar projects. my email is richard_beazley@fwuk.fwc.com if you want to engage in more discussion.
Member for
18 years 6 months
Member for18 years6 months
Submitted by Oliver Melling on Wed, 2007-12-12 05:20
If you have a rough schedule, then compare the project to similar jobs completed in the past and do a top-down estimate.
If you think it is going to cost around £50 million, then apportion the budget to the end products and divide the budget between the different resource disciplines/expenses/P&E that youre going to employ/procure etc. (Dont forget to escalate the costs in-line with inflation)
Divide the resource budgets by an assumed rate of pay and then you will have budgeted man-hours. Profile this against your rough schedule and you will get a resource profile to base your camp size upon.
One question, surely a Mega Project should have estimators or cost engineers?
Member for
21 years 1 monthRE: Estimating Total Construction Manpower
Hi Richard
Interesting problem you have there!
As your project is not even at the "questimate stage" any number chucked into the ring is as good as the next.
At at this stage of the work, your two educated quesses are the best you can do untill you can get some lower level estimating/costing organised.
Try basing the camp size and its services on an average of your two numbers, spread out equally over all the projects, then as the estimates develope update your original number. Its the best that can be achieved at this stage of the project.
But at the same make sure the layout and area of the camp / services can be easily changed modified to reflect increases / degreases in numbers etc.
It never ceases to amaze once we planners have "developed" a number, others will start to produce their numbers and so the estimate will clarify etc, but make sure your management understand what your numbers are based on and how they have been developed:- (its called diping hands in the blood).
Regards
John L.
Member for
24 years 5 monthsRE: Estimating Total Construction Manpower
Hi Oliver,
Appreciate your quick response! And you are absolutely right. The reality is that we are the Project Management Contractors/Consultants. The client, who has all the estimators, cost engineers etc have given us no information at all, though we do have rough figures for total budget.
They have no plans to give us the schedule because it is not firm enough to plan with...!! Again we have a very rough one page schedule, which has been overtaken by events. Each of the projects has a completely different sponsor, financing arrangements etc. Its going to be challenging to say the least! They are working on estimates and the minute I have those I can work it out!
I guess I need to search our archives and dig out data from similar projects. my email is richard_beazley@fwuk.fwc.com if you want to engage in more discussion.
Member for
18 years 6 monthsRE: Estimating Total Construction Manpower
If you have a rough schedule, then compare the project to similar jobs completed in the past and do a top-down estimate.
If you think it is going to cost around £50 million, then apportion the budget to the end products and divide the budget between the different resource disciplines/expenses/P&E that youre going to employ/procure etc. (Dont forget to escalate the costs in-line with inflation)
Divide the resource budgets by an assumed rate of pay and then you will have budgeted man-hours. Profile this against your rough schedule and you will get a resource profile to base your camp size upon.
One question, surely a Mega Project should have estimators or cost engineers?