Yes it is okay to define Financial period equal to the durations of the Project and define a batch for weekly cut-off. Make sure to run Store performance period every cut-off date define after the update of Progress.
I am working on a computer that has Suretrak 3.0b and I need to store period performance. This version does not seem to have the tools> store period performance menu structure of P3 which I have used in the past.
Does anybody know how to store period performance in this version of Suretrak?
You have do do it every week or every month depending on the period/time interval of your choice. It will be from your last store Period Performance to your current data date.
Member for
16 yearsRE: How to use Store Period Performance in P3?
Thank you Rodel for your response.
Member for
19 yearsRE: How to use Store Period Performance in P3?
Christopher,
Yes it is okay to define Financial period equal to the durations of the Project and define a batch for weekly cut-off. Make sure to run Store performance period every cut-off date define after the update of Progress.
Member for
16 yearsRE: How to use Store Period Performance in P3?
Hi Rodel!
Is it ok to consider the Financial period equal to the duration of the project making
Project start = Batch start date
Project Finish = Batch Finish Date
ex. PS= 01-Sept-07
PF= 30-Nov-07
Financial period =every week
so it will create 12 financial periods.
Please guide me.
Thanks
Member for
15 years 5 monthsRE: How to use Store Period Performance in P3?
Hello!
I am working on a computer that has Suretrak 3.0b and I need to store period performance. This version does not seem to have the tools> store period performance menu structure of P3 which I have used in the past.
Does anybody know how to store period performance in this version of Suretrak?
Thanks,
Cameron
Member for
17 years 11 monthsRE: How to use Store Period Performance in P3?
For setting up financial period, how can it be done in P3?
I cant select admin and financial period on P3 menu.
Could you mind to give me more information about this?
Thank you very much
Member for
19 yearsRE: How to use Store Period Performance in P3?
Mercer,
Before you can use Store Period Performance in P3e/P5/P6 you need to setup your financial period first.
Ex: monthly
a) Select Admin on your P5 Menu and click Financial Period.
b) Change the Batch Start Date(ie: 01-Sep-07)
c) Change the Batch End Date (ie: 30-Nov-07)
d) Click every month and change to 1
e) Click Batch Create
Note: It should create 3 Financial Period and rename it to Sep 07, Oct 07 and Nov 07.
f) Click Close
Then:
1) Select Edit -> Users Preferences
2) Select Application Tab
3) On Select Financial Period to view in column change it to Sep 07 to Nov 07.
You can use store Tools-> Store Period Performance every month cut off and you can view these financial period into columns.
Hope this help,
Rodel
Member for
17 years 11 monthsRE: How to use Store Period Performance in P3?
Dear Jerry
Thank you very much for your reply and useful information.
Mercer
Member for
19 years 1 monthRE: How to use Store Period Performance in P3?
Sum Lap key,
Tools > Store Period Performance
You have do do it every week or every month depending on the period/time interval of your choice. It will be from your last store Period Performance to your current data date.
Then you go to
Edit > Period Performance to view.
Regards,
-j- erry
Member for
17 years 11 monthsRE: How to use Store Period Performance in P3?
So do you know what and how to use of store period performance in P3?
Member for
19 years 1 monthRE: How to use Store Period Performance in P3?
Hi Sum Lap Key,
I remember we can only compare activity by activity, but not in a report or excel. Maybe in P5 we can?
Regards,
Jerry