Thanks mangesh,
I could recover 1800 activities out of a max 2500 activities. Surprisingly the previous project & the current project have same number of files & are of nearly equal size.
Paul, Thanks for the batching info, i will inform about its effectiveness today.
Cheers
Dattatreya
If pfx does not work you may want to try and batch it.
There is an article on my web site on this process.
Primavera also put out a fully automatic method of batching but it never worked for me. The programme is in the installation CD.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
Hi
Dattareya try using the repair utility by Name PFXW found in P3 progs folder, hope it may help.
cheers
mangesh