You can enter the ACTUAL WORK (hours) by changing the VIEW to TASK USAGE. On the right-hand side of the screen, you will see the cells that enable you to input the actual hours completed, on whatever days you choose. This will then automatically calculate the % Work Complete (hours). If you then change the remaining task duration, this will automatically change the % Complete (duration). However, you must be careful, because when you change the remaining duration, you are also likely to automatically change the Remaining Work (hours) - thus altering the % Work Complete.
There is no One-Button solution. If it is a Fixed Unit task, then changing the duration will automatically change the hours. If you dont want this to happen, then you must change the task-type to that of Fixed Work.
thanks for trying to help me but my tasks in the project are fixed units tasks when i did what u said i found out that % complete and % work complete are the same value while its a project for installing pipes and cables and some other stuff like air conditioing units
so i really can get it and im the consultant which is playing a part with the project owner and i have to follow the contractor if he is behinde the schedual or not??
% complete is duration and % work complete is resources or hrs. There are many ways of entering progress. You can double click the activity and enter percent complete from general tab of task information dialog box or by inserting column to show % work complete and % complete. Another way is to display the custom form icon from toolbars. View-> Toolbars-> Custom Form. Then select the form Work tracking.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Ahmed,
You can enter the ACTUAL WORK (hours) by changing the VIEW to TASK USAGE. On the right-hand side of the screen, you will see the cells that enable you to input the actual hours completed, on whatever days you choose. This will then automatically calculate the % Work Complete (hours). If you then change the remaining task duration, this will automatically change the % Complete (duration). However, you must be careful, because when you change the remaining duration, you are also likely to automatically change the Remaining Work (hours) - thus altering the % Work Complete.
There is no One-Button solution. If it is a Fixed Unit task, then changing the duration will automatically change the hours. If you dont want this to happen, then you must change the task-type to that of Fixed Work.
James.
thanks for trying to help me but my tasks in the project are fixed units tasks when i did what u said i found out that % complete and % work complete are the same value while its a project for installing pipes and cables and some other stuff like air conditioing units
so i really can get it and im the consultant which is playing a part with the project owner and i have to follow the contractor if he is behinde the schedual or not??
Ahmed,
% complete is duration and % work complete is resources or hrs. There are many ways of entering progress. You can double click the activity and enter percent complete from general tab of task information dialog box or by inserting column to show % work complete and % complete. Another way is to display the custom form icon from toolbars. View-> Toolbars-> Custom Form. Then select the form Work tracking.
HTH,
Rodel