We have recently discussed the problem again with ASTA Support. They have stated that this has not been resolved in the new V8. I am still waiting for my updated disc.
I will test this problem when I receive the new CD.
I have found problems recently using Summary Bars to show actual / planned progress. IE compare actual dates against Baseline dates.
The actual dates had gone past the original baseline dates (LATE AGAIN!!). There was still work to be carried out as shown on the Baseline Prog but the Planned Work indicated 100%. (Should have read 98.7% - worked out manually)
After several attempts trying to resolve myself I called ASTA TECH department. 4 Days later they stated that this would be sorted in the next version.
STILL WAITING.......
This is the first problem I have encounted with Progress on Summary Bar. But, I still maintain that Powerproject allows the user full control of as-built/progress reporting to give detailed acceptable programmes to the client. Which we all know - WE MUST KEEP HAPPY - They pay the bills.
Regards
Gavin
Member for
23 years 6 months
Member for23 years7 months
Submitted by David Bordoli on Mon, 2003-12-29 09:46
As far as I am aware Powerproject uses a method similar to ‘Planned Progress Monitoring’ to roll up progress to summary and expanded bars.
Tim – you are correct in saying that the method does not take account of criticality but we should remember that many users of Powerproject (and any other software) often do not always fully link their projects and even may just use them as a means of producing ‘Ganntt Charts’.
The criticisms of Planned Progress Monitoring are well documented but I think it’s not that bad. At least it is a relatively objective way in which to roll up progress (not only when considering summary and expanded bars) to assess a project’s current position.
Member for
23 years 2 monthsRE: Power Project (Team Plan) Progress Bar
Just a quick update on my last comment.
We have recently discussed the problem again with ASTA Support. They have stated that this has not been resolved in the new V8. I am still waiting for my updated disc.
I will test this problem when I receive the new CD.
Member for
23 years 2 monthsRE: Power Project (Team Plan) Progress Bar
I have found problems recently using Summary Bars to show actual / planned progress. IE compare actual dates against Baseline dates.
The actual dates had gone past the original baseline dates (LATE AGAIN!!). There was still work to be carried out as shown on the Baseline Prog but the Planned Work indicated 100%. (Should have read 98.7% - worked out manually)
After several attempts trying to resolve myself I called ASTA TECH department. 4 Days later they stated that this would be sorted in the next version.
STILL WAITING.......
This is the first problem I have encounted with Progress on Summary Bar. But, I still maintain that Powerproject allows the user full control of as-built/progress reporting to give detailed acceptable programmes to the client. Which we all know - WE MUST KEEP HAPPY - They pay the bills.
Regards
Gavin
Member for
23 years 6 monthsRE: Power Project (Team Plan) Progress Bar
Tim / Guest
As far as I am aware Powerproject uses a method similar to ‘Planned Progress Monitoring’ to roll up progress to summary and expanded bars.
Tim – you are correct in saying that the method does not take account of criticality but we should remember that many users of Powerproject (and any other software) often do not always fully link their projects and even may just use them as a means of producing ‘Ganntt Charts’.
The criticisms of Planned Progress Monitoring are well documented but I think it’s not that bad. At least it is a relatively objective way in which to roll up progress (not only when considering summary and expanded bars) to assess a project’s current position.
Regards
David
dbordoli@burofour.co.uk
Visit Buro Four on the web.