Can any body tell how to load a resource and prepare resource loading schedule,
indirect labour schedule and direct labour schedule?
plz help me .if its long answer plz tell me the refrence.
thansk mr David it works perfectly well with google advanced search
regards
deb
Hi There;
For search option in PP please check this:
http://www.planningplanet.com/forum/forum_post.asp?Cat=3&Top=22552.
I think it helps for the time being.
Regards
i fully agree with Bijaya , search option in planning planet will definitely help planners to have exactly the information that they are looking to else a lot of hard work by senior planners are wasted.
regards
deb
thanks mr.bijaya and mr.Akin Adurosakin for the help
regards
deb
I mean the SEARCH function should be functional.
It seems there is a need of SEARCH function in Planning Plannet.
Try the link below; the result could be helpfull.
http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=2&Top=26460.
Regards,
Akin Adurosakin
Nigeria
If you have resource loaded your activities, you have done the most time consuming part. In fact the S curve is already there now - and what you need to how to view it.
Press the button "Resource/cost profile" which usually appear on to with bar chart icon on top. If you dont see it, just go to View and then Ressource Profile.
You will see the profile at the bottom of the screen. Click "Display" button and then choose curve. If you also want histogram, choose that as well.
There are various filters and selection you can then apply depending on your need.
Good luck